[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143850":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1143850,800,1,"单选题","某施工项目的商品混凝土目标成本是 420000 元(目标产量 500m3， 目标单价 800 元\u002Fm3， 预计损耗率为 5%)， 实际成本是 511680 元(实际产量 600m3， 实际单价 820 元\u002Fm3， 实际损耗率为 4%)。 若采用因素分析法进行成本分析(因素的排列顺序是： 产量、 单价、 损耗量)， 则由于产量提高增加的成本是（） 元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","4920",false,{"key":16,"text":17,"correct":14},"B","12600",{"key":19,"text":20,"correct":21},"C","84000",true,{"key":23,"text":24,"correct":14},"D","91680","",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]