[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143846":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1143846,800,1,"单选题","按“制造成本法” 进行核算项目成本， 作为期间费用的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目管理人员的工资",false,{"key":16,"text":17,"correct":14},"B","项目人员的培训费用",{"key":19,"text":20,"correct":14},"C","场地清理费用",{"key":22,"text":23,"correct":24},"D","企业总部的管理费",true,"",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]