[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143844":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143844,800,2,"多选题","某工程施工期间发生工程变更， 导致措施项目费用调整， 下列调整措施正确的有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","安全文明施工费按照实际发生变化的措施项目调整，不得浮动",true,{"key":16,"text":17,"correct":18},"B","安全文明施工费按照实际发生变化的措施项目调整，可以浮动",false,{"key":20,"text":21,"correct":18},"C","总价计算的措施项目费，按实际发生变化的措施项目调整",{"key":23,"text":24,"correct":14},"D","工程设计变更引起施工方案改变，并使措施项目发生变化的，承包人提出调整措施项目费的，应事先将拟实施的方案提交发包人确认",{"key":26,"text":27,"correct":14},"E","承包人未事先将拟实施的方案提交给发包人，视为放弃调整","ADE","",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]