[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143832":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1143832,800,1,"单选题","根据《建设工程工程量清单计价规范》 (GB50500-2013)， 在施工中因发包人原因导致工期延误的， 计划进度日期后续工程的价格调整原则是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","应采用造价信息差额调整法",false,{"key":16,"text":17,"correct":14},"B","采用计划进度日期与实际进度日期两者的较低者",{"key":19,"text":20,"correct":14},"C","如果没有超过15%，则不做调整",{"key":22,"text":23,"correct":24},"D","采用计划进度日期与实际进度日期两者的较高者",true,"",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]