[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143824":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1143824,800,1,"单选题","下列合同类型中， 适用于灾后重建或对施工内容、 经济指标不确定的工程项目的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","固定总价合同",false,{"key":16,"text":17,"correct":14},"B","固定单价合同",{"key":19,"text":20,"correct":14},"C","变动单价合同",{"key":22,"text":23,"correct":24},"D","成本加酬金合同",true,"成本加酬金合同的合同价款包括成本和酬金两部分，双方在专用条款内约定成本构成和酬金的计算方法。成本加酬金合同适用于灾后重建、新型项目或对施工内容、经济指标不确定的工程项目。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]