[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143769":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1143769,800,1,"单选题","当高层建筑的玻璃幕墙安装与主体结构施工交叉作业时， 在主体结构的施工层下应设置防护网； 在距离地面约（ ） 高度处， 应设置挑出宽度不小于（ ） 的水平防护网",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3m，5m",false,{"key":16,"text":17,"correct":18},"B","3m，6m",true,{"key":20,"text":21,"correct":14},"C","4m，5m",{"key":23,"text":24,"correct":14},"D","4m，6m","当高层建筑的玻璃幕墙安装与主体结构施工交叉作业时，在主体结构的施工层下方应设置防护网；在距离地面约3m高度处，应设置挑出宽度≥6m的水平防护网。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]