[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143748":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143748,800,2,"多选题","下列关于模板工程施工安全的技术要求的说法中， 正确的有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","脚手架或操作平台上临时堆放的模板不宜超过2层",false,{"key":16,"text":17,"correct":18},"B","六级以上风力时，应停止高空作业",true,{"key":20,"text":21,"correct":14},"C","同条件养护试件强度达到规定要求时，直接由技术负责人批准拆模",{"key":23,"text":24,"correct":18},"D","设计无要求时，模板的拆除可按先支的后拆、后支的先拆进行",{"key":26,"text":27,"correct":14},"E","后张法预应力混凝土结构或构件的侧模应在预应力张拉完毕拆除","BD","",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]