[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143709":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1143709,800,1,"单选题","单位工程进度计划应在（） 领导下编制。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","监理工程师",false,{"key":16,"text":17,"correct":14},"B","总监理工程师",{"key":19,"text":20,"correct":14},"C","项目经理",{"key":22,"text":23,"correct":24},"D","项目技术负责人",true,"单位工程进度计划，由项目经理组织，在项目技术负责人领导下编制。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]