[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143707":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1143707,800,1,"单选题","工期十分紧迫， 在工作面、 资源允许情况下， 宜采用的施工组织形式是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","等节奏流水施工",false,{"key":16,"text":17,"correct":14},"B","成倍节拍流水施工",{"key":19,"text":20,"correct":14},"C","依次施工",{"key":22,"text":23,"correct":24},"D","平行施工",true,"",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]