[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143625":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1143625,800,1,"单选题","二级动火应由（） 组织拟定防火安全技术措施。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目安全管理部门",false,{"key":16,"text":17,"correct":18},"B","项目责任工程师",true,{"key":20,"text":21,"correct":14},"C","施工单位技术负责人",{"key":23,"text":24,"correct":14},"D","项目负责人","各级动火审批程序： （1）一级动火作业：由项目负责人组织编制防火安全技术方案，填写动火申请表，报企业安全管理部门审查批准后，方可动火。 （2）二级动火作业：由项目责任工程师组织拟定防火安全技术措施，填写动火申请表，报项目安全管理部门和项目负责人审查批准后，方可动火。 （3）三级动火作业：由所在班组填写动火申请表，经项目安全管理部门和项目责任工程师批准后，方可动火。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]