[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143576":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1143576,800,1,"单选题","锤击沉桩法施工， 不同规格钢筋混凝土预制桩的沉桩顺序是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","先大后小，先短后长",false,{"key":16,"text":17,"correct":14},"B","先小后大，先长后短",{"key":19,"text":20,"correct":21},"C","先大后小，先长后短",true,{"key":23,"text":24,"correct":14},"D","先小后大，先短后长","沉桩顺序应按先深后浅、先大后小、先长后短、先密后疏的次序进行；对于密集桩群，从中间开始分头向四周或两边对称施打；当一侧毗邻建筑物时，由毗邻建筑物处向另一方向施打。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]