[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143571":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1143571,800,1,"单选题","泥浆护壁法钻孔灌注桩施工流程中， 第二次清孔是在（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","下钢筋笼和导管后",true,{"key":16,"text":17,"correct":18},"B","成孔清除废浆.泥渣后",false,{"key":20,"text":21,"correct":18},"C","质量验收后",{"key":23,"text":24,"correct":18},"D","孔位校正后","泥浆护壁法钻孔灌注桩施工工艺流程：场地平整→桩位放线→开挖浆池.浆沟→护筒埋设→钻机就位.孔位校正→成孔.泥浆循环.清除废浆.泥渣→清孔换浆→终孔验收→下钢筋笼和钢导管→第二次清孔→浇筑水下混凝土→成桩。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]