[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143550":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1143550,800,1,"单选题","建筑物基坑采用钎探法验槽时， 钎杆每打入土层（ ） mm， 应记录一次锤击数。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","200",false,{"key":16,"text":17,"correct":14},"B","250",{"key":19,"text":20,"correct":21},"C","300",true,{"key":23,"text":24,"correct":14},"D","350","钎探法； 采用直径22?25mm钢筋制作的钢钎；普通锤子，重量8～10kg；锤举高度一般为50cm，自由下落； 钎杆每打入土层30cm时，记录一次锤击数。钎探深度以设计为依据；如设计无规定时，一般钎点按纵横间距1.5m梅花形布设，深度为2.1m。 打完的钎孔，经过质量检查人员和有关工长检查孔深与记录无误后，用盖孔块盖住孔眼。当设计、勘察和施工方共同验槽办理完验收手续后，方可灌孔。钎探后的孔要用砂灌实。 填土应从场地最低处开始，由下而上整个宽度分层铺填。每层虚铺厚度应根据夯实机械确定。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]