[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143529":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1143529,800,1,"单选题","下列关于防水工程施工完成后的检查与检验， 说法正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","屋面防水层施工完成后，应在雨后或持续淋水1h内进行检查",false,{"key":16,"text":17,"correct":14},"B","有可能蓄水试验的屋面，其蓄水时间为12h",{"key":19,"text":20,"correct":21},"C","厨房、厕浴间防水层完成后，应做24h蓄水试验",true,{"key":23,"text":24,"correct":14},"D","墙面间歇淋水试验应达到20min以上不渗漏","防水层完工后，应在雨后或持续淋水2h后（有可能作蓄水检验的屋面，其蓄水时间应≥24h），检查屋面有无渗漏、积水和排水系统是否畅通，施工质量符合要求方可进行防水层验收。 厨房、厕浴间防水层完成后，应做24h蓄水试验，确认无渗漏时再做保护层和面层。设备与饰面层施工完后还应在其上继续做第二次24h蓄水试验，达到最终无渗漏和排水畅通为合格，方可进行正式验收。墙面间歇淋水试验应达到30min以上不渗漏。",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]