[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143526":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143526,800,2,"多选题","无粘结预应力施工包含的工序有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","预应力筋下料",true,{"key":16,"text":17,"correct":18},"B","预留孔道",false,{"key":20,"text":21,"correct":14},"C","预应力筋张拉",{"key":23,"text":24,"correct":18},"D","孔道灌浆",{"key":26,"text":27,"correct":14},"E","锚头处理","ACE","无粘结预应力施工：它的特点是不需预留孔道和灌浆，施工简单等。在无粘结预应力施工中，主要工作是无粘结预应力箭的铺设张拉和锚固区的处理。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]