[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143421":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143421,800,2,"多选题","关于抹灰工程施工要求的说法， 正确的有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","抹灰用的石膏熟化期不应少于15d",true,{"key":16,"text":17,"correct":14},"B","室内墙面、柱面和门洞口阳角做法，当设计无要求时，应用1:2水泥砂浆做暗护角，高度不应低于2m，每侧宽度不应小于50mm",{"key":19,"text":20,"correct":21},"C","抹灰用的水泥强度等级应不小于42.5MPa",false,{"key":23,"text":24,"correct":21},"D","可以使用特细砂",{"key":26,"text":27,"correct":21},"E","水泥砂浆抹灰层应在湿润条件下养护，一般应在抹灰48h后进行养护","AB","",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]