[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143368":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143368,800,2,"多选题","关于主体结构混凝土浇筑的说法， 正确的有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","混凝土自高处倾落的自由高度，不宜超过3m",false,{"key":16,"text":17,"correct":14},"B","浇筑高度超过1m时，应采用串筒、溜管、溜槽等装置",{"key":19,"text":20,"correct":21},"C","浇筑与柱和墙连成整体的梁、板时，应在柱、墙浇筑完毕后停歇1~1.5h，再继续浇筑",true,{"key":23,"text":24,"correct":21},"D","混凝土泵车应尽量靠近浇筑地点，浇筑时应由远至近",{"key":26,"text":27,"correct":21},"E","浇筑竖向结构混凝土前，应先在底部填以不大于30mm厚与混凝土砂浆成分相同的水泥砂浆","CDE","A、B：粗骨料粒径大于 25mm 时，浇筑高度不宜超过 3m；粒径小于 25mm 时，不宜超过 6m。不能满足要求时，应加设串筒、溜管、溜槽等装置@##",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]