[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143356":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143356,800,2,"多选题","关于预制构件连接的说法， 正确的是（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","灌浆施工时，环境温度不应低于5℃",true,{"key":16,"text":17,"correct":18},"B","连接部位温度低于5℃时，应采取加热保温措施",false,{"key":20,"text":21,"correct":18},"C","灌浆作业应采用压浆法从上口灌注",{"key":23,"text":24,"correct":18},"D","浆料从排浆孔排浆时，应及时封堵注浆孔",{"key":26,"text":27,"correct":14},"E","灌浆料应在制备后30min内用完","AE","",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]