[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143255":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1143255,800,1,"单选题","采用锤击沉桩法打预制桩时， 当桩端达到坚硬粘性土时， 桩的入土深度的控制方法是（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","只控制贯入度",false,{"key":16,"text":17,"correct":18},"B","以控制贯入度为主，以标高为辅",true,{"key":20,"text":21,"correct":14},"C","只控制标高",{"key":23,"text":24,"correct":14},"D","以控制标高为主，以贯入度为辅","",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]