[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143226":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143226,800,2,"多选题","基坑（槽） 挖至基底设计标高并清理后， 参加验槽的单位有（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","建设单位",true,{"key":16,"text":17,"correct":18},"B","质量监督机构",false,{"key":20,"text":21,"correct":14},"C","勘察单位",{"key":23,"text":24,"correct":14},"D","施工单位",{"key":26,"text":27,"correct":14},"E","监理单位","ACDE","",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]