[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143202":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143202,800,2,"多选题","关于地下连续墙支护的施工要求说法， 正确的有（）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","适用于周边环境条件很复杂的深基坑",true,{"key":16,"text":17,"correct":14},"B","单元槽段长度宜为4~6m",{"key":19,"text":20,"correct":21},"C","钢筋笼吊放就位后应及时浇筑混凝土，间隔时间不宜大于2h",false,{"key":23,"text":24,"correct":21},"D","灌注混凝土时混凝土强度应按设计要求强度等级进行配制",{"key":26,"text":27,"correct":14},"E","墙顶宜高出设计标高300~500mm","ABE","地下连续墙施工要求： ①地下连续墙单元槽段长度宜为 4~6m。 ②导管水平布置距离不应大于 3m，距槽段端部不应大于 1.5m； ③钢筋笼吊放就位后应及时浇筑混凝土，间隔不宜大于 4h； ④混凝土强度等级应比设计强度提高 1 个等级进行配制，混凝土浇筑面高出设计标高 300~500mm。地下连续墙混凝土强度等级宜取 C30~C40。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]