[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143200":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143200,800,2,"多选题","关于地下连续墙墙底注浆的说法， 正确的是（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","墙体混凝土强度达到设计要求75%后方可进行墙底注浆",false,{"key":16,"text":17,"correct":18},"B","单元槽内注浆管不应少于2根",true,{"key":20,"text":21,"correct":18},"C","注浆管下端应伸到槽底200~500mm",{"key":23,"text":24,"correct":18},"D","注浆压力应控制在2MPa以内",{"key":26,"text":27,"correct":14},"E","注浆总量达到设计要求80%以上时，可终止注浆","BCD","地下连续墙墙底注浆： （1）墙体混凝土强度达到设计要求后方可进行墙底注浆 （2）单元槽内注浆管不应少于 2 根 （3）注浆管下端应伸到槽底 200~500mm （4）注浆压力应控制在 2MPa 以内 （5）注浆总量达到设计要求或注浆量达到设计要求 80%以上且 压力达到 2MPa 时，可终止注浆",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]