[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143170":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1143170,800,1,"单选题","关于建筑物沉降观测的周期和时间的说法， 正确的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","应在基础底板混凝土浇筑完毕后开始观测",false,{"key":16,"text":17,"correct":14},"B","民用高层建筑每加高1层观测1次",{"key":19,"text":20,"correct":14},"C","施工中若暂时停工，仅需在重新开工时观测1次",{"key":22,"text":23,"correct":24},"D","竣工后运营阶段，在第一年应观测3~4次",true,"",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]