[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143169":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1143169,800,1,"单选题","A 点高程 40.150m,B 点高程 41.220m。施工单位测量场内 M 点高程： 从 A 点引测， 前视读数 1.10m,后视读数 1.4m： 现从 B 点校核 M 点高程， 后视读数 1.10m， 前视读数应为（） m。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1.25",false,{"key":16,"text":17,"correct":14},"B","1.37",{"key":19,"text":20,"correct":14},"C","1.49",{"key":22,"text":23,"correct":24},"D","1.87",true,"",{"id":6,"name":27,"category":28,"favorite":29},"一建建筑工程实务","建筑工程",0]