[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143158":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143158,800,2,"多选题","施工测量现场基本工作有（）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","测角",true,{"key":16,"text":17,"correct":14},"B","测距",{"key":19,"text":20,"correct":14},"C","测高差",{"key":22,"text":23,"correct":24},"D","倾斜线的测设",false,{"key":26,"text":27,"correct":24},"E","建筑物细部点平面位置的测设","ABC","大中型的施工项目，应先建立场区控制网，再分别建立每栋建筑物的施工控制网；以建筑物平面的控制点为基础测设建筑物的主轴线，根据主轴线再进行建筑物细部放样。",{"id":6,"name":31,"category":32,"favorite":33},"一建建筑工程实务","建筑工程",0]