[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-147333":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},147333,80,1,"单选题","( )是由于过去的决策所引起的，已经发生的成本，它们无法由现在或将来的经营决策所改变，决策时无需考虑。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","不相关成本",false,{"key":16,"text":17,"correct":18},"B","沉没成本",true,{"key":20,"text":21,"correct":14},"C","相关成本",{"key":23,"text":24,"correct":14},"D","付现成本","A项，不相关成本与决策无关，在分析评价时无需考虑；C项，相关成本是指与特定的决策有关，在分析评价时必须考虑的成本；D项，付现成本是指那些由于某项决策而引起的需要在未来用现金支付的成本。",{"id":6,"name":27,"category":28,"favorite":29},"(高级) 运输经济","经济金融",0]