[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-799-23":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":627},{"id":5,"name":6,"category":7,"favorite":8},799,"一建建设工程项目管理","建筑工程",0,23,50,2721,[13,38,53,68,83,97,109,121,135,149,161,173,185,197,209,221,233,245,253,267,282,296,306,315,330,345,359,371,386,397,406,418,433,441,451,463,471,481,493,503,515,527,537,547,557,568,580,589,599,613],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":36,"analysis":37},1141647,2,"多选题","施工作业交底是最基层的技术和管理交底活动，（ ）要对施工作业交底进行监督。",[19,23,27,30,33],{"key":20,"text":21,"correct":22},"A","业主方",false,{"key":24,"text":25,"correct":26},"B","施工总承包方",true,{"key":28,"text":29,"correct":22},"C","设计方",{"key":31,"text":32,"correct":26},"D","工程监理机构",{"key":34,"text":35,"correct":22},"E","政府主管部门","BD","",{"id":39,"libraryId":5,"type":15,"typeLabel":16,"stem":40,"options":41,"answer":52,"analysis":37},1141648,"某建设工程项目施工采用了施工总承包方式，其中的幕墙工程，设备安装工程分别进行了专业分包，对幕墙工程施工质量实施监督控制的主体是（ ）等。",[42,44,46,48,50],{"key":20,"text":43,"correct":22},"幕墙玻璃供应商",{"key":24,"text":45,"correct":26},"建设行政主管部门",{"key":28,"text":47,"correct":26},"幕墙设计单位",{"key":31,"text":49,"correct":22},"设备安装单位",{"key":34,"text":51,"correct":26},"建设单位","BCE",{"id":54,"libraryId":5,"type":15,"typeLabel":16,"stem":55,"options":56,"answer":67,"analysis":37},1141649,"下列施工现场质量检查，属于实测法检查的有（ ）。",[57,59,61,63,65],{"key":20,"text":58,"correct":22},"肉眼观察墙面喷涂的密实度",{"key":24,"text":60,"correct":22},"用敲击工具检查地面砖铺贴的密实度",{"key":28,"text":62,"correct":26},"用直尺检查地面的平整度",{"key":31,"text":64,"correct":26},"用锤吊线检查墙面的垂直度",{"key":34,"text":66,"correct":22},"现场检测混凝土试件的抗压强度","CD",{"id":69,"libraryId":5,"type":15,"typeLabel":16,"stem":70,"options":71,"answer":82,"analysis":37},1141650,"根据实践经验的总结，施工作业质量自控的有效制度包括（ ）。",[72,74,76,78,80],{"key":20,"text":73,"correct":26},"质量挂牌制度",{"key":24,"text":75,"correct":26},"质量例会制度",{"key":28,"text":77,"correct":26},"质量会诊制度",{"key":31,"text":79,"correct":26},"质量样板制度",{"key":34,"text":81,"correct":22},"质量互检制度","ABCD",{"id":84,"libraryId":5,"type":85,"typeLabel":86,"stem":87,"options":88,"answer":24,"analysis":37},1141651,1,"单选题","关于钢筋保护层厚度检测的说法，正确的是（ ）。( 2015真题 )",[89,91,93,95],{"key":20,"text":90,"correct":22},"检测机构部位由监理确定",{"key":24,"text":92,"correct":26},"梁类应抽取构件数量的2%且不少于5个构件",{"key":28,"text":94,"correct":22},"板类构件应抽取构件数量的5%且不少于2个构件",{"key":31,"text":96,"correct":22},"必须采用无损检测方法",{"id":98,"libraryId":5,"type":85,"typeLabel":86,"stem":99,"options":100,"answer":20,"analysis":37},1141652,"关于主体结构工程现场质量检测的说法，正确的是（ ）。 2016",[101,103,105,107],{"key":20,"text":102,"correct":26},"按照统计方法评定混凝土强度时，同一强度等级试件的留置数量不宜少于10组。按非统计方法评定时，留置数量不宜少于3组",{"key":24,"text":104,"correct":22},"砌体工程中，普通砖5万块，多孔砖10万块各为一检验批，抽检数量为1组",{"key":28,"text":106,"correct":22},"对梁板类构件，应抽取构件数量的1%且不少于5个构件进行钢筋保护层厚度检测",{"key":31,"text":108,"correct":22},"混凝土预制构件结构性能检测应按同一工艺生产的不超过100件且不超过3个月的同类产品为一检验批",{"id":110,"libraryId":5,"type":85,"typeLabel":86,"stem":111,"options":112,"answer":24,"analysis":37},1141654,"对于重要的或对工程质量有重大影响的工序，应严格执行（ ）的“三检”制度。2014",[113,115,117,119],{"key":20,"text":114,"correct":22},"事前检查、事中检查、事后检查",{"key":24,"text":116,"correct":26},"自检、互检、专检",{"key":28,"text":118,"correct":22},"工序检查、分项检查、分部检查",{"key":31,"text":120,"correct":22},"操作者自检、质量员检查、监理工程师检查",{"id":122,"libraryId":5,"type":15,"typeLabel":16,"stem":123,"options":124,"answer":134,"analysis":37},1141655,"根据法律和合同，对施工单位的施工质量行为和效果实施监督控制的相关主体有（ ）。2014",[125,126,128,130,132],{"key":20,"text":51,"correct":26},{"key":24,"text":127,"correct":26},"监理单位",{"key":28,"text":129,"correct":26},"设计单位",{"key":31,"text":131,"correct":22},"材料设备供应商",{"key":34,"text":133,"correct":26},"政府的工程质量监督部门","ABCE",{"id":136,"libraryId":5,"type":15,"typeLabel":16,"stem":137,"options":138,"answer":134,"analysis":37},1141656,"某施工项目为实施成本管理收集了以下资料，其中可以作为编制施工成本计划依据的有（ ）。2014",[139,141,143,145,147],{"key":20,"text":140,"correct":26},"施工预算",{"key":24,"text":142,"correct":26},"签订的工程合同",{"key":28,"text":144,"correct":26},"分包合同",{"key":31,"text":146,"correct":22},"施工图预算",{"key":34,"text":148,"correct":26},"资源市场价格",{"id":150,"libraryId":5,"type":85,"typeLabel":86,"stem":151,"options":152,"answer":31,"analysis":37},1141659,"按照我国现行规定，对检验批主控项目抽检合格率必须达到（ ），才能具备合格条件。",[153,155,157,159],{"key":20,"text":154,"correct":22},"85%",{"key":24,"text":156,"correct":22},"90%",{"key":28,"text":158,"correct":22},"95%",{"key":31,"text":160,"correct":26},"100%",{"id":162,"libraryId":5,"type":85,"typeLabel":86,"stem":163,"options":164,"answer":28,"analysis":37},1141660,"某工程进行检验批验收时，发现某框架梁截面尺寸与原设计图纸尺寸不符，但经原设计单位核算，仍能满足结构安全性及使用性要求。则该检验批（ ）。",[165,167,169,171],{"key":20,"text":166,"correct":22},"应重新施工",{"key":24,"text":168,"correct":22},"应经施工单位和业主协商确认是否予以验收，其经济责任由业主承担",{"key":28,"text":170,"correct":26},"可直接予以验收",{"key":31,"text":172,"correct":22},"必须进行加固处理后重新组织验收",{"id":174,"libraryId":5,"type":85,"typeLabel":86,"stem":175,"options":176,"answer":20,"analysis":37},1141661,"根据《建筑工程施工质量验收统一标准》（GB 50300-2001），对于通过返修可以解决质量缺陷的检验批，应（ ）。",[177,179,181,183],{"key":20,"text":178,"correct":26},"按验收程序重新进行验收",{"key":24,"text":180,"correct":22},"按技术处理方案和协商文件进行验收",{"key":28,"text":182,"correct":22},"经检测单位检测鉴定后予以验收",{"key":31,"text":184,"correct":22},"经设计单位复核后予以验收",{"id":186,"libraryId":5,"type":85,"typeLabel":86,"stem":187,"options":188,"answer":28,"analysis":37},1141663,"下列关于施工过程质量验收的说明，正确的是（ ）。",[189,191,193,195],{"key":20,"text":190,"correct":22},"施工过程质量验收是以分部工程的施工质量为基本验收单元",{"key":24,"text":192,"correct":22},"当个别检验批发现试块强度不满足要求时，应不能通过验收",{"key":28,"text":194,"correct":26},"当检测鉴定达不到设计要求，但经原设计单位核算仍能满足结构安全和使用功能的检验批，可予以验收",{"key":31,"text":196,"correct":22},"通过返修处理仍不能满足安全使用要求的分部工程，可降低标准验收，并扣除适当工程款",{"id":198,"libraryId":5,"type":85,"typeLabel":86,"stem":199,"options":200,"answer":31,"analysis":37},1141664,"对某办公大楼二层一施工段内的框架柱钢筋制作的质量，应按一个（ ）进行验收。",[201,203,205,207],{"key":20,"text":202,"correct":22},"单位工程",{"key":24,"text":204,"correct":22},"分部工程",{"key":28,"text":206,"correct":22},"分项工程",{"key":31,"text":208,"correct":26},"检验批",{"id":210,"libraryId":5,"type":85,"typeLabel":86,"stem":211,"options":212,"answer":20,"analysis":37},1141665,"分部工程应由（ ）组织施工单位项目负责人和技术、质量负责人等进行验收。",[213,215,217,219],{"key":20,"text":214,"correct":26},"总监理工程师",{"key":24,"text":216,"correct":22},"监理工程师",{"key":28,"text":218,"correct":22},"项目经理",{"key":31,"text":220,"correct":22},"业主",{"id":222,"libraryId":5,"type":85,"typeLabel":86,"stem":223,"options":224,"answer":20,"analysis":37},1141666,"某工程由于安装的生产设备存在质量缺陷，导致其中某分部工程质量不合格，施工单位在更换了该生产设备后，该分部工程应（ ）。",[225,227,229,231],{"key":20,"text":226,"correct":26},"按验收程序，重新组织检查验收",{"key":24,"text":228,"correct":22},"经有资质的检测单位检测鉴定后，予以验收",{"key":28,"text":230,"correct":22},"征得建设单位同意后，可予以验收",{"key":31,"text":232,"correct":22},"按技术处理方案和协商文件，进行验收",{"id":234,"libraryId":5,"type":85,"typeLabel":86,"stem":235,"options":236,"answer":28,"analysis":37},1141668,"根据《统一标准》，建筑工程质量验收划分为（ ）。",[237,239,241,243],{"key":20,"text":238,"correct":22},"分部工程、分项工程和检验批",{"key":24,"text":240,"correct":22},"分部工程、分项工程、隐蔽工程和检验批",{"key":28,"text":242,"correct":26},"单位工程、分部工程、分项工程和检验批",{"key":31,"text":244,"correct":22},"单位工程、分部工程、分项工程、隐蔽工程和检验批",{"id":246,"libraryId":5,"type":85,"typeLabel":86,"stem":247,"options":248,"answer":20,"analysis":37},1141669,"根据我国相关规范的规定，对于通过翻修可以解决质量缺陷的检验批，应（ ）。",[249,250,251,252],{"key":20,"text":178,"correct":26},{"key":24,"text":180,"correct":22},{"key":28,"text":182,"correct":22},{"key":31,"text":184,"correct":22},{"id":254,"libraryId":5,"type":15,"typeLabel":16,"stem":255,"options":256,"answer":67,"analysis":37},1141670,"设计单位在建设工程项目施工阶段进行质量控制和验收的主要工作内容包括（ ）。",[257,259,261,263,265],{"key":20,"text":258,"correct":22},"控制原材料、半成品质量",{"key":24,"text":260,"correct":22},"参与审核主体结构的施工方案",{"key":28,"text":262,"correct":26},"对变更设计图纸进行控制",{"key":31,"text":264,"correct":26},"纠正施工中发现的设计问题",{"key":34,"text":266,"correct":22},"完善工程竣工图",{"id":268,"libraryId":5,"type":15,"typeLabel":16,"stem":269,"options":270,"answer":281,"analysis":37},1141671,"下列施工现场质量检查的内容中，属于“三检”制度范围的有（ ）。",[271,273,275,277,279],{"key":20,"text":272,"correct":26},"自检自查",{"key":24,"text":274,"correct":22},"巡视检查",{"key":28,"text":276,"correct":26},"互检互查",{"key":31,"text":278,"correct":22},"平行检查",{"key":34,"text":280,"correct":26},"专职管理人员的质量检查","ACE",{"id":283,"libraryId":5,"type":15,"typeLabel":16,"stem":284,"options":285,"answer":52,"analysis":37},1141672,"建设工程项目施工质量检查验收时，应重点检查的施工质量保证资料包括（ ）。",[286,288,290,292,294],{"key":20,"text":287,"correct":22},"施工日志",{"key":24,"text":289,"correct":26},"施工检测资料",{"key":28,"text":291,"correct":26},"测量复核资料",{"key":31,"text":293,"correct":22},"工地施工例会会议纪要",{"key":34,"text":295,"correct":26},"原材料检测资料",{"id":297,"libraryId":5,"type":15,"typeLabel":16,"stem":298,"options":299,"answer":67,"analysis":37},1141673,"施工质量验收中需要对观感进行验收的有（ ）。",[300,301,302,303,304],{"key":20,"text":208,"correct":22},{"key":24,"text":206,"correct":22},{"key":28,"text":204,"correct":26},{"key":31,"text":202,"correct":26},{"key":34,"text":305,"correct":22},"单项工程",{"id":307,"libraryId":5,"type":15,"typeLabel":16,"stem":308,"options":309,"answer":36,"analysis":37},1141674,"下列施工质量验收环节中，应由专业监理工程师组织施工单位项目专业质量负责人等进行验收的有（ ）。",[310,311,312,313,314],{"key":20,"text":204,"correct":22},{"key":24,"text":206,"correct":26},{"key":28,"text":305,"correct":22},{"key":31,"text":208,"correct":26},{"key":34,"text":202,"correct":22},{"id":316,"libraryId":5,"type":15,"typeLabel":16,"stem":317,"options":318,"answer":329,"analysis":37},1141675,"建筑工程施工质量验收中，检验批质量验收的内容包括（ ）。",[319,321,323,325,327],{"key":20,"text":320,"correct":26},"质量资料",{"key":24,"text":322,"correct":26},"主控项目",{"key":28,"text":324,"correct":26},"一般项目",{"key":31,"text":326,"correct":22},"允许偏差项目",{"key":34,"text":328,"correct":22},"观感质量","ABC",{"id":331,"libraryId":5,"type":15,"typeLabel":16,"stem":332,"options":333,"answer":344,"analysis":37},1141676,"下列关于建设工程项目施工质量验收的表述中，正确的有（ ）。",[334,336,338,340,342],{"key":20,"text":335,"correct":26},"工程质量验收均应在施工单位自行检查评定的基础上进行",{"key":24,"text":337,"correct":22},"参加工程施工质量验收的各方人员由政府部门确定",{"key":28,"text":339,"correct":22},"工程外观质量通过现场检查后由质量监督机构确认",{"key":31,"text":341,"correct":26},"隐蔽工程应在隐蔽前由施工单位通知有关单位进行验收，并形成验收文件",{"key":34,"text":343,"correct":26},"单位工程施工质量应该符合相关验收规范","ADE",{"id":346,"libraryId":5,"type":15,"typeLabel":16,"stem":347,"options":348,"answer":134,"analysis":37},1141677,"工程项目分部工程质量验收合格的基本条件是（ ）。",[349,351,353,355,357],{"key":20,"text":350,"correct":26},"所含分项工程验收合格",{"key":24,"text":352,"correct":26},"质量控制资料完整",{"key":28,"text":354,"correct":26},"观感质量验收应符合要求",{"key":31,"text":356,"correct":22},"主控项目质量检验合格",{"key":34,"text":358,"correct":26},"涉及安全和使用功能的分部工程检验结果符合规定",{"id":360,"libraryId":5,"type":85,"typeLabel":86,"stem":361,"options":362,"answer":24,"analysis":37},1141679,"根据《建筑工程施工质量验收统一标准》（GB50300-2013），关于检验批质量验收合格的说法，正确的是（ ）。( 2015真题 )",[363,365,367,369],{"key":20,"text":364,"correct":22},"可由监理员组织验收",{"key":24,"text":366,"correct":26},"应具有完整的施工操作依据，质量检查记录",{"key":28,"text":368,"correct":22},"主控项目不需全部检验合格",{"key":31,"text":370,"correct":22},"一般项目的检查具有否决权",{"id":372,"libraryId":5,"type":15,"typeLabel":16,"stem":373,"options":374,"answer":385,"analysis":37},1141680,"关于施工项目分部工程质量验收的说法，正确的有（ ）。 2016",[375,377,379,381,383],{"key":20,"text":376,"correct":26},"分部工程应由总监理工程师组织施工单位项目负责人和项目技术负责人等进行验收",{"key":24,"text":378,"correct":22},"设计单位项目负责人和施工单位技术、质量部门负责人应参加设备各安装分部的工程验收",{"key":28,"text":380,"correct":26},"勘察、设计单位项目负责人和施工单位技术、质量部门负责人应参加地基与基础分部工程验收",{"key":31,"text":382,"correct":26},"分部工程验收需对地基基础、主体结构、设备安装分部工程进行见证取样试验或抽样检测",{"key":34,"text":384,"correct":26},"分部工程验收需要对观感质量进行验收，并综合给出质量评价","ACDE",{"id":387,"libraryId":5,"type":85,"typeLabel":86,"stem":388,"options":389,"answer":20,"analysis":37},1141681,"如工程质量不符合要求，经过加固处理后外形尺寸改变，但能满足安全使用要求，其处理方法是（ ）。2014",[390,391,393,395],{"key":20,"text":180,"correct":26},{"key":24,"text":392,"correct":22},"虽有质量缺陷，应予以验收",{"key":28,"text":394,"correct":22},"仍按验收不合格处理",{"key":31,"text":396,"correct":22},"先返工处理，重新进行验收",{"id":398,"libraryId":5,"type":85,"typeLabel":86,"stem":399,"options":400,"answer":20,"analysis":37},1141682,"根据《建设工程施工质量验收统一标准》（GB50300-2013），分项工程的质量验收应由（ ）组织进行。2014",[401,402,403,404],{"key":20,"text":216,"correct":26},{"key":24,"text":218,"correct":22},{"key":28,"text":214,"correct":22},{"key":31,"text":405,"correct":22},"建设单位项目负责人",{"id":407,"libraryId":5,"type":85,"typeLabel":86,"stem":408,"options":409,"answer":24,"analysis":37},1141686,"当无驻厂监督时，未做结构性能检查的装配式混凝土预制构件，进场时应按规定进行实体检验，关于检验数量的说法，正确的是（）。2018真题",[410,412,414,416],{"key":20,"text":411,"correct":22},"同一类型不超过500个为一批，每批随机抽取1个",{"key":24,"text":413,"correct":26},"同一类型不超过1000个为一批，每批随机抽取1个",{"key":28,"text":415,"correct":22},"同一类型不超过500个为一批，每批随机抽取3个",{"key":31,"text":417,"correct":22},"同一类型不超过1000个为一批，每批随机抽取3个",{"id":419,"libraryId":5,"type":15,"typeLabel":16,"stem":420,"options":421,"answer":432,"analysis":37},1141687,"对于不做结构性能检验的混凝土预制构件，当无驻厂监督时，预制构件进场时应按规定进行实体检验，其检验内容包括（）。2018真题",[422,424,426,428,430],{"key":20,"text":423,"correct":22},"预埋铁件型号、数量",{"key":24,"text":425,"correct":22},"外形尺寸偏差",{"key":28,"text":427,"correct":26},"受力钢筋的数量、规格、间距",{"key":31,"text":429,"correct":26},"受力钢筋的保护层厚度",{"key":34,"text":431,"correct":26},"混凝土强度","CDE",{"id":434,"libraryId":5,"type":85,"typeLabel":86,"stem":435,"options":436,"answer":31,"analysis":37},1141691,"工程项目竣工质量验收的基本对象是（ ），并且也是工程项目投入使用前的最后一次验收，其重要性不言而喻。",[437,438,439,440],{"key":20,"text":208,"correct":22},{"key":24,"text":206,"correct":22},{"key":28,"text":204,"correct":22},{"key":31,"text":202,"correct":26},{"id":442,"libraryId":5,"type":85,"typeLabel":86,"stem":443,"options":444,"answer":28,"analysis":37},1141692,"建设工程项目竣工验收应由（ ）组织。",[445,446,448,449],{"key":20,"text":127,"correct":22},{"key":24,"text":447,"correct":22},"政府质量监督机构",{"key":28,"text":51,"correct":26},{"key":31,"text":450,"correct":22},"施工单位",{"id":452,"libraryId":5,"type":85,"typeLabel":86,"stem":453,"options":454,"answer":24,"analysis":37},1141693,"按现行有关规定，应对工程中涉及结构安全的材料及施工内容进行（ ）。",[455,457,459,461],{"key":20,"text":456,"correct":22},"封样鉴定",{"key":24,"text":458,"correct":26},"见证取样检测",{"key":28,"text":460,"correct":22},"模拟试件检测",{"key":31,"text":462,"correct":22},"同条件养护检测",{"id":464,"libraryId":5,"type":85,"typeLabel":86,"stem":465,"options":466,"answer":31,"analysis":37},1141694,"（ ）是工程项目竣工质量验收的基本对象。",[467,468,469,470],{"key":20,"text":208,"correct":22},{"key":24,"text":206,"correct":22},{"key":28,"text":204,"correct":22},{"key":31,"text":202,"correct":26},{"id":472,"libraryId":5,"type":85,"typeLabel":86,"stem":473,"options":474,"answer":24,"analysis":37},1141695,"单位工程完工后，施工单位自行组织有关人员进行质量检查评定，在具备竣工验收条件后，向（ ）提交工程验收报告。",[475,476,477,479],{"key":20,"text":127,"correct":22},{"key":24,"text":51,"correct":26},{"key":28,"text":478,"correct":22},"勘察设计单位",{"key":31,"text":480,"correct":22},"政府建设工程质量监督部门",{"id":482,"libraryId":5,"type":85,"typeLabel":86,"stem":483,"options":484,"answer":24,"analysis":37},1141696,"根据《建筑工程施工质量验收统一标准》（GB 50300—2001）对涉及结构安全和使用功能的重要分部工程应进行（ ）。",[485,487,489,491],{"key":20,"text":486,"correct":22},"化学成分测定",{"key":24,"text":488,"correct":26},"抽样检测",{"key":28,"text":490,"correct":22},"破坏性试验",{"key":31,"text":492,"correct":22},"观感质量验收",{"id":494,"libraryId":5,"type":85,"typeLabel":86,"stem":495,"options":496,"answer":20,"analysis":37},1141697,"单位工程完工后，（ ）应组织检查、评定，符合验收标准后，向建设单位提交验收申请。",[497,498,499,501],{"key":20,"text":450,"correct":26},{"key":24,"text":129,"correct":22},{"key":28,"text":500,"correct":22},"建设主管部门",{"key":31,"text":502,"correct":22},"质量监督机构",{"id":504,"libraryId":5,"type":85,"typeLabel":86,"stem":505,"options":506,"answer":24,"analysis":37},1141698,"施工验收质量控制是对工程项目中各类已完工程质量的控制，该工作应在（ ）进行。",[507,509,511,513],{"key":20,"text":508,"correct":22},"单位工程竣工验收阶段",{"key":24,"text":510,"correct":26},"项目施工全过程各阶段",{"key":28,"text":512,"correct":22},"隐蔽工程验收阶段",{"key":31,"text":514,"correct":22},"分部工程验收阶段",{"id":516,"libraryId":5,"type":85,"typeLabel":86,"stem":517,"options":518,"answer":28,"analysis":37},1141699,"当建设工程按合同要求全部完成后，承包人向发包人提供了完整的竣工资料和竣工验收报告，发包人应在收到竣工验收报告后（ ）天内组织验收。",[519,521,523,525],{"key":20,"text":520,"correct":22},"7",{"key":24,"text":522,"correct":22},"14",{"key":28,"text":524,"correct":26},"28",{"key":31,"text":526,"correct":22},"30",{"id":528,"libraryId":5,"type":85,"typeLabel":86,"stem":529,"options":530,"answer":31,"analysis":37},1141700,"建设工程项目竣工工程质量验收时，对于涉及结构安全和功能的主要分部分项工程应进行（ ）。",[531,533,534,536],{"key":20,"text":532,"correct":22},"外观检查",{"key":24,"text":458,"correct":22},{"key":28,"text":535,"correct":22},"剥露检验",{"key":31,"text":488,"correct":26},{"id":538,"libraryId":5,"type":85,"typeLabel":86,"stem":539,"options":540,"answer":31,"analysis":37},1141701,"涉及结构安全的试块、试件以及有关材料，应按规定进行（ ）。",[541,543,545,546],{"key":20,"text":542,"correct":22},"功能性检测",{"key":24,"text":544,"correct":22},"破坏性检测",{"key":28,"text":488,"correct":22},{"key":31,"text":458,"correct":26},{"id":548,"libraryId":5,"type":85,"typeLabel":86,"stem":549,"options":550,"answer":20,"analysis":37},1141702,"建设单位应在工程竣工验收前（ ）个工作日前，将验收时间、地点、验收组名单书面通知该工程的工程质量监督机构。",[551,552,554,555],{"key":20,"text":520,"correct":26},{"key":24,"text":553,"correct":22},"3",{"key":28,"text":522,"correct":22},{"key":31,"text":556,"correct":22},"15",{"id":558,"libraryId":5,"type":85,"typeLabel":86,"stem":559,"options":560,"answer":31,"analysis":37},1141703,"建设单位应在工程竣工验收前（ ）个工作日前将验收时间、地点、验收组名单书面通知该工程的工程质量监督机构。",[561,563,565,567],{"key":20,"text":562,"correct":22},"4",{"key":24,"text":564,"correct":22},"5",{"key":28,"text":566,"correct":22},"6",{"key":31,"text":520,"correct":26},{"id":569,"libraryId":5,"type":85,"typeLabel":86,"stem":570,"options":571,"answer":28,"analysis":37},1141704,"房屋建筑工程和市政基础设施工程验收合格后，建设单位应将验收报告报送政府管理部门（ ）。",[572,574,576,578],{"key":20,"text":573,"correct":22},"确认",{"key":24,"text":575,"correct":22},"审核",{"key":28,"text":577,"correct":26},"备案",{"key":31,"text":579,"correct":22},"复评",{"id":581,"libraryId":5,"type":85,"typeLabel":86,"stem":582,"options":583,"answer":28,"analysis":37},1141705,"建设单位应当自建设工程竣工验收合格之日起（ ）日内，将建设工程竣工验收报告和规划、公安消防、环境保护等部门出具的认可文件或准许使用文件，报建设行政主管部门或者其他相关部门备案。",[584,585,586,587],{"key":20,"text":520,"correct":22},{"key":24,"text":522,"correct":22},{"key":28,"text":556,"correct":26},{"key":31,"text":588,"correct":22},"21",{"id":590,"libraryId":5,"type":85,"typeLabel":86,"stem":591,"options":592,"answer":31,"analysis":37},1141706,"根据《建设工程质量管理条例》，各类房屋建筑工程和市政基础设施工程应在竣工验收合格之日起（ ）日内，将验收文件报建设行政主管部门备案。",[593,595,596,598],{"key":20,"text":594,"correct":22},"45",{"key":24,"text":526,"correct":22},{"key":28,"text":597,"correct":22},"20",{"key":31,"text":556,"correct":26},{"id":600,"libraryId":5,"type":15,"typeLabel":16,"stem":601,"options":602,"answer":82,"analysis":37},1141707,"建设工程竣工验收应当具备的条件有（ ）。",[603,605,607,609,611],{"key":20,"text":604,"correct":26},"有施工单位签署的工程保修书",{"key":24,"text":606,"correct":26},"有完整的技术档案和施工管理资料",{"key":28,"text":608,"correct":26},"有勘察、设计、监理、施工、质监站等分别签署的质量合格文件",{"key":31,"text":610,"correct":26},"已完成建设工程设计和合同约定的各项内容",{"key":34,"text":612,"correct":22},"材料合格证和试验报告",{"id":614,"libraryId":5,"type":15,"typeLabel":16,"stem":615,"options":616,"answer":385,"analysis":37},1141708,"工程项目竣工质量验收的依据有（ ）。",[617,619,621,623,625],{"key":20,"text":618,"correct":26},"专业工程施工质量验收规范",{"key":24,"text":620,"correct":22},"施工组织设计",{"key":28,"text":622,"correct":26},"工程施工质量验收统一标准",{"key":31,"text":624,"correct":26},"工程施工承包合同",{"key":34,"text":626,"correct":26},"施工图纸",[628,631,634,637,640,643],{"id":85,"name":629,"category":7,"favorite":630},"领导干部任职前廉政法规知识测试题",92,{"id":632,"name":633,"category":7,"favorite":85},595,"建筑结构与设备",{"id":635,"name":636,"category":7,"favorite":85},715,"招标采购专业知识与法律法规",{"id":638,"name":639,"category":7,"favorite":85},848,"市政方向-通用基础",{"id":641,"name":642,"category":7,"favorite":8},534,"BIM工程师",{"id":644,"name":642,"category":7,"favorite":8},535]