[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"lib-799-16":3},{"library":4,"page":9,"limit":10,"total":11,"questions":12,"related":589},{"id":5,"name":6,"category":7,"favorite":8},799,"一建建设工程项目管理","建筑工程",0,16,50,2721,[13,38,52,64,76,91,103,115,127,139,151,162,174,181,192,199,211,223,235,243,255,264,276,288,296,302,313,325,337,352,367,382,397,407,419,431,446,454,466,478,486,498,513,521,530,539,547,554,569,581],{"id":14,"libraryId":5,"type":15,"typeLabel":16,"stem":17,"options":18,"answer":36,"analysis":37},1141254,2,"多选题","某单代号网络图如下图所示，存在的错误有（ ）。",[19,23,26,30,33],{"key":20,"text":21,"correct":22},"A","多个起点节点",true,{"key":24,"text":25,"correct":22},"B","有多余虚箭线",{"key":27,"text":28,"correct":29},"C","出现交叉箭线",false,{"key":31,"text":32,"correct":29},"D","没有终点节点",{"key":34,"text":35,"correct":29},"E","出现循环回路","AB","",{"id":39,"libraryId":5,"type":40,"typeLabel":41,"stem":42,"options":43,"answer":27,"analysis":37},1141258,1,"单选题","关于虚工作的说法，正确的是（ ）。( 2015真题 )",[44,46,48,50],{"key":20,"text":45,"correct":29},"虚工作只在双代号网络计划中存在",{"key":24,"text":47,"correct":29},"虚工作一般不消耗资源但占用时间",{"key":27,"text":49,"correct":22},"虚工作可以正确表达工作间逻辑关系",{"key":31,"text":51,"correct":29},"双代号时标网络计划中虚工作用波形表示",{"id":53,"libraryId":5,"type":40,"typeLabel":41,"stem":54,"options":55,"answer":20,"analysis":37},1141259,"（2020年真题）某双代号网络计划如下图，关键线路有（ ）条。",[56,58,60,62],{"key":20,"text":57,"correct":22},"3",{"key":24,"text":59,"correct":29},"1",{"key":27,"text":61,"correct":29},"2",{"key":31,"text":63,"correct":29},"4",{"id":65,"libraryId":5,"type":40,"typeLabel":41,"stem":66,"options":67,"answer":24,"analysis":37},1141260,"（2020年真题）各工作间逻辑关系表及相应双代号网图如下图。图中虛箭线的作用是（ ）。",[68,70,72,74],{"key":20,"text":69,"correct":29},"联系",{"key":24,"text":71,"correct":22},"区分",{"key":27,"text":73,"correct":29},"断路",{"key":31,"text":75,"correct":29},"指向",{"id":77,"libraryId":5,"type":15,"typeLabel":16,"stem":78,"options":79,"answer":90,"analysis":37},1141262,"（2020年真题）下列双代号网络图中，存在的绘图错误有（ ）",[80,82,84,86,88],{"key":20,"text":81,"correct":22},"存在多个起点节点",{"key":24,"text":83,"correct":22},"箭线交叉的方式错误",{"key":27,"text":85,"correct":29},"存在相同节点编号的工作",{"key":31,"text":87,"correct":29},"存在没有箭尾节点的箭线",{"key":34,"text":89,"correct":22},"存在多余的虚工作","ABE",{"id":92,"libraryId":5,"type":40,"typeLabel":41,"stem":93,"options":94,"answer":24,"analysis":37},1141263,"某工程双代号网络计划如下图所示,图中已标出每个节点的最早开始时间和最迟开始时间，该计划表明（ ）。",[95,97,99,101],{"key":20,"text":96,"correct":29},"工作1-2和工作1-4均为关键工作",{"key":24,"text":98,"correct":22},"工作1-4的自由时差为2",{"key":27,"text":100,"correct":29},"工作2-6和工作3-6均为关键工作",{"key":31,"text":102,"correct":29},"工作4-5的总时差和自由时差相等",{"id":104,"libraryId":5,"type":40,"typeLabel":41,"stem":105,"options":106,"answer":31,"analysis":37},1141264,"某工程网络计划中工作M的总时差为3天，自由时差为0。该计划执行过程中，只有工作M的实际进度拖后4天，则工作M的实际进度将其紧后工作的最早开始时间推迟和使总工期延长的时间分别为（ ）。",[107,109,111,113],{"key":20,"text":108,"correct":29},"3天和0天",{"key":24,"text":110,"correct":29},"3天和1天",{"key":27,"text":112,"correct":29},"4天和0天",{"key":31,"text":114,"correct":22},"4天和1天",{"id":116,"libraryId":5,"type":40,"typeLabel":41,"stem":117,"options":118,"answer":27,"analysis":37},1141265,"单代号网络图中工作的最早完成时间等于（ ）。",[119,121,123,125],{"key":20,"text":120,"correct":29},"该工作的各个紧前工作的最早完成时间的最大值",{"key":24,"text":122,"correct":29},"该工作的各个紧前工作的最早完成时间的最小值",{"key":27,"text":124,"correct":22},"该工作的最早开始时间加该工作的持续时间",{"key":31,"text":126,"correct":29},"该工作的最迟开始时间减该工作的自由时差",{"id":128,"libraryId":5,"type":40,"typeLabel":41,"stem":129,"options":130,"answer":20,"analysis":37},1141266,"某工程网络计划中，工作F的最早开始时间为第11天，持续时间为5天，工作F有三项紧后工作，它们的最早开始时间分别为第20天、第22天和第23天，最迟开始时间分别为第21天、第24天和第27天，则工作F的总时差和自由时差分别为（ ）。",[131,133,135,137],{"key":20,"text":132,"correct":22},"5；4",{"key":24,"text":134,"correct":29},"11；7",{"key":27,"text":136,"correct":29},"5；5",{"key":31,"text":138,"correct":29},"4；4",{"id":140,"libraryId":5,"type":40,"typeLabel":41,"stem":141,"options":142,"answer":31,"analysis":37},1141267,"在某工程双代号网络计划中，工作N的最早开始时间和最迟开始时间分别为第20天和第25天，其持续时间为9天。该工作有两项紧后工作，它们的最早开始时间分别为第32开和第34天，则工作N的总时差和自由时差分别为（ ）天。",[143,145,147,149],{"key":20,"text":144,"correct":29},"3和0",{"key":24,"text":146,"correct":29},"3和2",{"key":27,"text":148,"correct":29},"5和0",{"key":31,"text":150,"correct":22},"5和3",{"id":152,"libraryId":5,"type":40,"typeLabel":41,"stem":153,"options":154,"answer":20,"analysis":37},1141268,"已知工程网络计划中某工作的自由时差为5d，总时差为7d。监理工程师在检查进度时发现只有该工作实际进度拖延，且影响工期3d，则该工作实际进度比计划进度拖延（ ）d。",[155,157,159,161],{"key":20,"text":156,"correct":22},"10",{"key":24,"text":158,"correct":29},"8",{"key":27,"text":160,"correct":29},"7",{"key":31,"text":57,"correct":29},{"id":163,"libraryId":5,"type":40,"typeLabel":41,"stem":164,"options":165,"answer":27,"analysis":37},1141269,"某工作的总时差为3天，自由时差为2天，施工过程中只有该工作延误了2天，则下列说法中正确的是（ ）。",[166,168,170,172],{"key":20,"text":167,"correct":29},"总工期不延长，该工作的紧后工作延误1天",{"key":24,"text":169,"correct":29},"总工期延误1天，该工作的紧后工作延误1天",{"key":27,"text":171,"correct":22},"总工期不延长，该工作的紧后工作不延误",{"key":31,"text":173,"correct":29},"总工期延误1天，该工作的紧后工作不延误",{"id":175,"libraryId":5,"type":40,"typeLabel":41,"stem":176,"options":177,"answer":24,"analysis":37},1141270,"某双代号网络计划如下图所示(时间：天)，则工作D的自由时差是（ ）天。",[178,179,180],{"key":20,"text":57,"correct":29},{"key":24,"text":61,"correct":22},{"key":27,"text":59,"correct":29},{"id":182,"libraryId":5,"type":40,"typeLabel":41,"stem":183,"options":184,"answer":31,"analysis":37},1141272,"某工程网络计划中工作B的持续时间为5天，其两项紧前工作的最早完成时间分别为第6天和第8天，则工作B的最早完成时间为第（ ）天。",[185,187,188,190],{"key":20,"text":186,"correct":29},"6",{"key":24,"text":158,"correct":29},{"key":27,"text":189,"correct":29},"11",{"key":31,"text":191,"correct":22},"13",{"id":193,"libraryId":5,"type":40,"typeLabel":41,"stem":194,"options":195,"answer":37,"analysis":37},1141273,"由分部工程双代号网络计划如下图所示，则工作C的自由时差为（ ）天。",[196,197,198],{"key":20,"text":59,"correct":29},{"key":24,"text":61,"correct":29},{"key":27,"text":57,"correct":29},{"id":200,"libraryId":5,"type":40,"typeLabel":41,"stem":201,"options":202,"answer":27,"analysis":37},1141274,"工程网络计划中工作的自由时差和总时差均表示工作所具有的机动时间，如果计划工期等于计算工期，则（ ）。",[203,205,207,209],{"key":20,"text":204,"correct":29},"自由时差等于总时差",{"key":24,"text":206,"correct":29},"自由时差大于总时差",{"key":27,"text":208,"correct":22},"自由时差不会超过总时差",{"key":31,"text":210,"correct":29},"自由时差可能大于也可能小于总时差",{"id":212,"libraryId":5,"type":40,"typeLabel":41,"stem":213,"options":214,"answer":20,"analysis":37},1141275,"在工程网络计划中，如果某项工作的拖延时间超过其自由时差但没有超过总时差，则（ ）。",[215,217,219,221],{"key":20,"text":216,"correct":22},"该项工作使其紧后工作不能按最早时间开始",{"key":24,"text":218,"correct":29},"该项工作的延误会影响工程总工期",{"key":27,"text":220,"correct":29},"该项工作会变成关键工作",{"key":31,"text":222,"correct":29},"该项工作对后续工作及工程总工期无影响",{"id":224,"libraryId":5,"type":40,"typeLabel":41,"stem":225,"options":226,"answer":20,"analysis":37},1141276,"工期泛指完成任务所需要的时间，在其类型中，（ ）用TC表示。",[227,229,231,233],{"key":20,"text":228,"correct":22},"计算工期",{"key":24,"text":230,"correct":29},"要求工期",{"key":27,"text":232,"correct":29},"总工期",{"key":31,"text":234,"correct":29},"计划工期",{"id":236,"libraryId":5,"type":40,"typeLabel":41,"stem":237,"options":238,"answer":24,"analysis":37},1141277,"某工程双代号时标网络计划如下图所示（时间单位：周），在不影响总工期的前提下，工作B可利用的机动时间为（ ）周。",[239,240,241,242],{"key":20,"text":59,"correct":29},{"key":24,"text":61,"correct":22},{"key":27,"text":57,"correct":29},{"key":31,"text":63,"correct":29},{"id":244,"libraryId":5,"type":40,"typeLabel":41,"stem":245,"options":246,"answer":20,"analysis":37},1141278,"某工程网络计划中，工作M的自由时差为2天，总时差为5天。实施中进度检查时发现该工作的持续时间延长了4天，则工作M的实际进度（ ）。",[247,249,251,253],{"key":20,"text":248,"correct":22},"不影响总工期，但将其紧后工作的最早开始时间推迟2天",{"key":24,"text":250,"correct":29},"既不影响总工期，也不影响其后续工作的正常进行",{"key":27,"text":252,"correct":29},"将使总工期延长4天，但不影响其后续工作的正常进行",{"key":31,"text":254,"correct":29},"将其后续工作的开始时间推迟4天，并使总工期延长1天",{"id":256,"libraryId":5,"type":40,"typeLabel":41,"stem":257,"options":258,"answer":20,"analysis":37},1141279,"某双代号网络计划中（以天为单位），工作K的最早开始时间为6，工作持续时间为4，工作M的最迟完成时间为22。工作持续时间为10，工作N的最迟完成时间为20，工作持续时间为5，已知工作K只有M，N两项紧后工作，工作K的总时差为（ ）天。",[259,260,261,263],{"key":20,"text":61,"correct":22},{"key":24,"text":57,"correct":29},{"key":27,"text":262,"correct":29},"5",{"key":31,"text":186,"correct":29},{"id":265,"libraryId":5,"type":40,"typeLabel":41,"stem":266,"options":267,"answer":20,"analysis":37},1141280,"某道路工程在进行基层和面层施工时，为了给面层铺设提供工作面和工作条件，需待基层铺设一定时间后才能进行面层摊铺，这种时间间隔是（ ）时距。",[268,270,272,274],{"key":20,"text":269,"correct":22},"STS",{"key":24,"text":271,"correct":29},"FTF",{"key":27,"text":273,"correct":29},"STF",{"key":31,"text":275,"correct":29},"FTS",{"id":277,"libraryId":5,"type":40,"typeLabel":41,"stem":278,"options":279,"answer":31,"analysis":37},1141281,"已知 A.B工作的紧后工作为 C. D，其持续时间分别为3天、4天、2天、5天，AB工作的最早开始时间为第6天、4天，则D工作的最早完成时间为第（ ）。",[280,282,284,286],{"key":20,"text":281,"correct":29},"10天",{"key":24,"text":283,"correct":29},"11天",{"key":27,"text":285,"correct":29},"13天",{"key":31,"text":287,"correct":22},"14天",{"id":289,"libraryId":5,"type":40,"typeLabel":41,"stem":290,"options":291,"answer":31,"analysis":37},1141282,"当修一条堤坝的护坡时，一定要等土堤自然沉降后才能修护坡，这种等待的时间间隔称为 （ ）时距。",[292,293,294,295],{"key":20,"text":273,"correct":29},{"key":24,"text":269,"correct":29},{"key":27,"text":271,"correct":29},{"key":31,"text":275,"correct":22},{"id":297,"libraryId":5,"type":40,"typeLabel":41,"stem":176,"options":298,"answer":24,"analysis":37},1141283,[299,300,301],{"key":20,"text":57,"correct":29},{"key":24,"text":61,"correct":22},{"key":27,"text":59,"correct":29},{"id":303,"libraryId":5,"type":40,"typeLabel":41,"stem":304,"options":305,"answer":20,"analysis":37},1141284,"某工程网络计划中工作M的总时差和自由时差分别为5d和3d，该计划执行过程中经检查发现只有工作M的实际进度拖后4d，则工作M的实际进度（ ）。",[306,308,310,312],{"key":20,"text":307,"correct":22},"不影响总工期，但将其紧后工作的最早开始时间推迟1d",{"key":24,"text":309,"correct":29},"将其紧后工作的最早开始时间推迟1d，并使总工期延长1d",{"key":27,"text":311,"correct":29},"不影响其后续工作的正常进行，但使总工期延长1d",{"key":31,"text":250,"correct":29},{"id":314,"libraryId":5,"type":40,"typeLabel":41,"stem":315,"options":316,"answer":31,"analysis":37},1141285,"某工程网络计划中，工作M 的总时差为5 天，自由时差为3 天。在计划执行情况的检查中，发现只有工作M 的实际进度拖后了4 天，则关于工作M 实际进度的说法，正确的是（ ）。",[317,319,321,323],{"key":20,"text":318,"correct":29},"使总工期拖后1天，使后续工作最早开始时间拖后1天",{"key":24,"text":320,"correct":29},"不影响总工期，也不影响后续工作的正常进行",{"key":27,"text":322,"correct":29},"使总工期拖后1天，但不影响后续工作的正常进行",{"key":31,"text":324,"correct":22},"不影响总工期，但使后续工作最早开始时间拖后1天",{"id":326,"libraryId":5,"type":40,"typeLabel":41,"stem":327,"options":328,"answer":31,"analysis":37},1141286,"单代号网络计划的自由时差等于（ ）。",[329,331,333,335],{"key":20,"text":330,"correct":29},"该工作与紧前工作时间间隔的最大值",{"key":24,"text":332,"correct":29},"该工作与紧后工作时间间隔的最大值",{"key":27,"text":334,"correct":29},"该工作与紧前工作时间间隔的最小值",{"key":31,"text":336,"correct":22},"该工作与紧后工作时间间隔的最小值",{"id":338,"libraryId":5,"type":15,"typeLabel":16,"stem":339,"options":340,"answer":351,"analysis":37},1141287,"在双代号时标网络计划中，（ ）。",[341,343,345,347,349],{"key":20,"text":342,"correct":22},"工作箭线左端节点所对应的时标值为该工作的最早开始时间",{"key":24,"text":344,"correct":29},"工作箭线右端节点所对应的时标值为该工作的最早完成时间",{"key":27,"text":346,"correct":22},"终点节点所对应的时标值为该网络计划的计划工期",{"key":31,"text":348,"correct":22},"波形线表示工作与其紧后工作之间的时间间隔",{"key":34,"text":350,"correct":22},"各项工作按最早开始时间绘制","ACDE",{"id":353,"libraryId":5,"type":15,"typeLabel":16,"stem":354,"options":355,"answer":366,"analysis":37},1141288,"某分部工程双代号时标网络计划如下图所示，该计划所提供的正确信息有（ ）。",[356,358,360,362,364],{"key":20,"text":357,"correct":22},"工作B的总时差为3",{"key":24,"text":359,"correct":22},"工作C的总时差为2",{"key":27,"text":361,"correct":22},"工作D为关键工作",{"key":31,"text":363,"correct":22},"工作E的总时差为3",{"key":34,"text":365,"correct":29},"工作G的自由时差为2","ABCD",{"id":368,"libraryId":5,"type":15,"typeLabel":16,"stem":369,"options":370,"answer":381,"analysis":37},1141290,"下图所示的双代号时标网络计划，执行到第4周末及第10周末时，检查其实际进度如，图中前锋线所示，检查结果表明（ ）。",[371,373,375,377,379],{"key":20,"text":372,"correct":22},"第4周末检查时工作A拖后1周，影响工期1周",{"key":24,"text":374,"correct":29},"第4周末检查时工作B拖后1周，但不影响工期",{"key":27,"text":376,"correct":29},"第10周末检查时工作I提前一周，可使工期提前1周",{"key":31,"text":378,"correct":29},"在第5周到第10周内，工作F和工作I的实际进度正常",{"key":34,"text":380,"correct":22},"第10周末检查时工作G拖后1周，但不影响工期","AE",{"id":383,"libraryId":5,"type":15,"typeLabel":16,"stem":384,"options":385,"answer":396,"analysis":37},1141291,"某工程双代号网络计划如下图所示（时间单位：天），图中已标出各项工作的最早开始时间ES和最迟开始时间LS。该计划表明（ ）。",[386,388,390,392,394],{"key":20,"text":387,"correct":22},"工作1-3的总时差和自由时差相等",{"key":24,"text":389,"correct":22},"工作2-6的总时差和自由时差相等",{"key":27,"text":391,"correct":29},"工作2-4和工作3-6均为关键工作",{"key":31,"text":393,"correct":22},"工作3-5的总时差和自由时差分别为2和0天",{"key":34,"text":395,"correct":22},"工作5-7的总时差和自由时差相等","ABDE",{"id":398,"libraryId":5,"type":40,"typeLabel":41,"stem":399,"options":400,"answer":20,"analysis":37},1141292,"某工作的最早开始时间是5，最早结束时间9，最迟开始时间7，则该工作的最迟完成时间是（ ）。",[401,402,404,405],{"key":20,"text":189,"correct":22},{"key":24,"text":403,"correct":29},"12",{"key":27,"text":191,"correct":29},{"key":31,"text":406,"correct":29},"14",{"id":408,"libraryId":5,"type":40,"typeLabel":41,"stem":409,"options":410,"answer":27,"analysis":37},1141294,"双代号时标网络计划中，当某工作之后有虚工作时，该工作的自由时差为（ ）。",[411,413,415,417],{"key":20,"text":412,"correct":29},"该工作的波形线的水平长度",{"key":24,"text":414,"correct":29},"本工作与紧后工作间波形线水平长度和的最大值",{"key":27,"text":416,"correct":22},"本工作与紧后工作间波形线水平长度和的最小值",{"key":31,"text":418,"correct":29},"后续所有线路段中波形线中水平长度和的最小值",{"id":420,"libraryId":5,"type":40,"typeLabel":41,"stem":421,"options":422,"answer":27,"analysis":37},1141295,"某双代号时标网络计划如下图，如 B、 D、I工作共用同一台施工机械且按B-D-I顺序施工，则对网络计划可能造成的影响是（ ）。 2016",[423,425,427,429],{"key":20,"text":424,"correct":29},"总工期不会延长，但施工机械会在现场闲置1周",{"key":24,"text":426,"correct":29},"总工期会延长1周，但施工机械在现场不会闲置",{"key":27,"text":428,"correct":22},"总工期不会延长，且施工机械在现场不会闲置",{"key":31,"text":430,"correct":29},"总工期会延长1周，且施工机械会在现场闲置1周",{"id":432,"libraryId":5,"type":15,"typeLabel":16,"stem":433,"options":434,"answer":445,"analysis":37},1141296,"某分部工程时标网络计划如下图所示，当计划执行到第3周未时和第6周未时，检查得到的实际进度如图中的实际进度前锋线所示，该图说明（ ）。",[435,437,439,441,443],{"key":20,"text":436,"correct":22},"第3周末检查时预计工期拖后一周",{"key":24,"text":438,"correct":29},"工作A和工作D在第4周至第6周内实际进度正常",{"key":27,"text":440,"correct":22},"第6周末检查时预计工期拖后一周",{"key":31,"text":442,"correct":29},"工作B和工作E在第4周至第6周内实际进度正常",{"key":34,"text":444,"correct":22},"第6周末检查时工作G实际进度拖后一周","ACE",{"id":447,"libraryId":5,"type":40,"typeLabel":41,"stem":448,"options":449,"answer":27,"analysis":37},1141297,"下列双代号时标网络计划中，关键线路有（ ）条。( 2015真题 )",[450,451,452,453],{"key":20,"text":262,"correct":29},{"key":24,"text":63,"correct":29},{"key":27,"text":57,"correct":22},{"key":31,"text":61,"correct":29},{"id":455,"libraryId":5,"type":40,"typeLabel":41,"stem":456,"options":457,"answer":31,"analysis":37},1141298,"某双代号网络计划中，工作A有两项紧后工作B和 C，工作B和工作C的最早开始时间分别为第13天和第15天，最迟开始时间分别为第19天和第21天；工作A与工作B和工作C的间隔时间分别为0天和2天。如果工作A实际进度拖延7天，则（ ）。 2016",[458,460,462,464],{"key":20,"text":459,"correct":29},"对工期没有影响",{"key":24,"text":461,"correct":29},"总工期延长2天",{"key":27,"text":463,"correct":29},"总工期延长3天",{"key":31,"text":465,"correct":22},"总工期延长1天",{"id":467,"libraryId":5,"type":40,"typeLabel":41,"stem":468,"options":469,"answer":27,"analysis":37},1141299,"某双代号网络计划中，假设计划工期等于计算工期，且工作M的开始节点和完成节点均为关键节点。关于工作M的说法，正确的是（ ）。 2016",[470,472,474,476],{"key":20,"text":471,"correct":29},"工作M是关键工作",{"key":24,"text":473,"correct":29},"工作M的自由时差为零",{"key":27,"text":475,"correct":22},"工作M的总时差等于自由时差",{"key":31,"text":477,"correct":29},"工作M的总时差大于自由时差",{"id":479,"libraryId":5,"type":40,"typeLabel":41,"stem":480,"options":481,"answer":27,"analysis":37},1141300,"某双代号网络计划中。工作M的最早开始时间和最迟开始时间分别为第12天和第15天，其持续时间为5天。工作M有3项紧后工作，它们的最早开始时间分别为第21天、第24天和第28天，则工作M的自由时差为（ ）天。 2016",[482,483,484,485],{"key":20,"text":59,"correct":29},{"key":24,"text":57,"correct":29},{"key":27,"text":63,"correct":22},{"key":31,"text":262,"correct":29},{"id":487,"libraryId":5,"type":40,"typeLabel":41,"stem":488,"options":489,"answer":24,"analysis":37},1141301,"某单代号网络计划如下图（时间单位：天），其计算工期为（ ）天。 2016",[490,492,494,496],{"key":20,"text":491,"correct":29},"20",{"key":24,"text":493,"correct":22},"26",{"key":27,"text":495,"correct":29},"22",{"key":31,"text":497,"correct":29},"24",{"id":499,"libraryId":5,"type":15,"typeLabel":16,"stem":500,"options":501,"answer":512,"analysis":37},1141302,"关于工作总时差、自由时差及相邻两工作间间隔时间关系的说法，正确的有（ ）。 2016",[502,504,506,508,510],{"key":20,"text":503,"correct":29},"工作的自由时差一定不超过其紧后工作的总时差",{"key":24,"text":505,"correct":22},"工作的自由时差一定不超过其相应的总时差",{"key":27,"text":507,"correct":29},"工作的总时差一定不超过其紧后工作的自由时差",{"key":31,"text":509,"correct":22},"工作的自由时差一定不超过其紧后工作之间的间隔时间",{"key":34,"text":511,"correct":29},"工作的总时差一定不超过其紧后工作之间的间隔时间","BD",{"id":514,"libraryId":5,"type":40,"typeLabel":41,"stem":515,"options":516,"answer":27,"analysis":37},1141304,"某工作有且仅有两个紧后工作 C、 D，其中C工作最早开始时间为10（计算坐标系,下同），最迟完成时间为18，持续时间为5天；D工作最早完成时间为18，最迟完成时间为20，持续时间为6天；该工作与C工作间的时间间隔为2天，与D工作间的时间间隔为4天，则该工作的总时差为（ ）天。2014",[517,518,519,520],{"key":20,"text":57,"correct":29},{"key":24,"text":63,"correct":29},{"key":27,"text":262,"correct":22},{"key":31,"text":186,"correct":29},{"id":522,"libraryId":5,"type":40,"typeLabel":41,"stem":523,"options":524,"answer":31,"analysis":37},1141305,"某工程双代号网络计划如下图，其计算工期是（ ）天。",[525,526,527,529],{"key":20,"text":189,"correct":29},{"key":24,"text":191,"correct":29},{"key":27,"text":528,"correct":29},"15",{"key":31,"text":495,"correct":22},{"id":531,"libraryId":5,"type":40,"typeLabel":41,"stem":532,"options":533,"answer":27,"analysis":37},1141306,"某单代号网络计划如下图，工作 A、D之间的时间间隔是（ ）天。",[534,536,537,538],{"key":20,"text":535,"correct":29},"0",{"key":24,"text":59,"correct":29},{"key":27,"text":61,"correct":22},{"key":31,"text":57,"correct":29},{"id":540,"libraryId":5,"type":40,"typeLabel":41,"stem":541,"options":542,"answer":27,"analysis":37},1141307,"某网路计划中，工作N的持续时间为6天，最迟完成时间为第25天，该工作三项紧前工作的最早完成时间分别为第10天，第12天和第13天，则工作N的总时差是（）天。2018真题",[543,544,545,546],{"key":20,"text":403,"correct":29},{"key":24,"text":158,"correct":29},{"key":27,"text":186,"correct":22},{"key":31,"text":63,"correct":29},{"id":548,"libraryId":5,"type":40,"typeLabel":41,"stem":549,"options":550,"answer":24,"analysis":37},1141308,"某双代号网络计划如下图（单位：天），则工作E的自由时差为（）天。2018真题",[551,552,553],{"key":20,"text":57,"correct":29},{"key":24,"text":61,"correct":22},{"key":27,"text":63,"correct":29},{"id":555,"libraryId":5,"type":15,"typeLabel":16,"stem":556,"options":557,"answer":568,"analysis":37},1141309,"某工程双代号网络计划如下图，已标出各项工作的最早开始时间（ESi-j）、最迟开始时间（LSi-j）和持续时间（Di-j）。2018真题该网络计划表明（）。2018真题",[558,560,562,564,566],{"key":20,"text":559,"correct":29},"工作C和工作E均为关键工作",{"key":24,"text":561,"correct":22},"工作B的总时差和自由时差相等",{"key":27,"text":563,"correct":22},"工作D的总时差和自由时差相等",{"key":31,"text":565,"correct":22},"工作G的总时差、自由时差分别为2天和0天",{"key":34,"text":567,"correct":22},"工作J的总时差和自由时差相等","BCDE",{"id":570,"libraryId":5,"type":40,"typeLabel":41,"stem":571,"options":572,"answer":27,"analysis":37},1141310,"某工程网络计划中，工作M的自由时差为2天，总时差为5天。进度检查时发现该工作的持续时间延长了4天，则工作M的实际进度（）。2018真题",[573,575,577,579],{"key":20,"text":574,"correct":29},"既不影响总工期，也不影响其紧后工作的正常进行",{"key":24,"text":576,"correct":29},"将使其紧后工作的开始时间推迟4天，并使总工期延长2天",{"key":27,"text":578,"correct":22},"不影响总工期，但其紧后工作的最早开始时间推迟2天",{"key":31,"text":580,"correct":29},"将使总工期延长4天，但不影响其紧后工作的正常进行",{"id":582,"libraryId":5,"type":40,"typeLabel":41,"stem":583,"options":584,"answer":27,"analysis":37},1141311,"某工作有三项紧后工作，持续时间分为4天、5天、6天，对应的最迟完成时间分别为第18天、第16天、第14天，则该工作的最迟完成时间是第（）天。2018真题",[585,586,587,588],{"key":20,"text":406,"correct":29},{"key":24,"text":403,"correct":29},{"key":27,"text":158,"correct":22},{"key":31,"text":186,"correct":29},[590,593,596,599,602,605],{"id":40,"name":591,"category":7,"favorite":592},"领导干部任职前廉政法规知识测试题",92,{"id":594,"name":595,"category":7,"favorite":40},595,"建筑结构与设备",{"id":597,"name":598,"category":7,"favorite":40},715,"招标采购专业知识与法律法规",{"id":600,"name":601,"category":7,"favorite":40},848,"市政方向-通用基础",{"id":603,"name":604,"category":7,"favorite":8},534,"BIM工程师",{"id":606,"name":604,"category":7,"favorite":8},535]