[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143847":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1143847,799,1,"单选题","对于采用单价合同招标的工程，如投标书中有明显的数字计算错误业主有权先做出修改在评标。当总价和早价的计算结果不一致时，正确的做法( )。（2013）",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","按市场价调整早价",false,{"key":16,"text":17,"correct":14},"B","分别调整单价和总价",{"key":19,"text":20,"correct":14},"C","以总价为准调整单价",{"key":22,"text":23,"correct":24},"D","以单价为准调整总价",true,"",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]