[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143843":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143843,799,2,"多选题","对建设周期一年半以上的工程项目，采用变动总价合同时，应考虑引起价格变化的因素有（）（2014）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","银行利率的调整",false,{"key":16,"text":17,"correct":18},"B","材料费的上涨",true,{"key":20,"text":21,"correct":18},"C","人工工资的上涨",{"key":23,"text":24,"correct":18},"D","国家政策改变引起的工程费用上涨",{"key":26,"text":27,"correct":14},"E","设计变更引起的费用变化","BCD","在工程施工承包招标时，施工期限一年左右的项目一般实行固定总价合同，通常不考虑价格调整问题，以签订合同时的单价和总价为准，物价上涨的风险全部由承包商承担。但是对建设周期一年半以上的工程项目，则应考虑下列因素引起的价格变化问题： ( 1 ) 劳务工资以及材料费用的上涨； ( 2 ) 其他影响工程造价的因素，如运输费、燃料费、电力等价格的变化； ( 3 ) 外汇汇率的不稳定；",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]