[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143797":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1143797,799,1,"单选题","在签订合同的谈判中，为了防范货币贬值或者通货膨胀的风险，招标人和中标人一般通过()约定风险分担方式（2013）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","确定价格调整条款",true,{"key":16,"text":17,"correct":18},"B","确定合同价格条款",false,{"key":20,"text":21,"correct":18},"C","调整工程范围",{"key":23,"text":24,"correct":18},"D","确定合同款支付方式","对于工期较长的建设工程，容易遭受货币贬值或通货膨胀等因素的影响，可能给承包人造成较大损失。价格调整条款可以比较公正地解决这一承包人无法控制的风险损失。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]