[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143795":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143795,799,2,"多选题","下列合同条款中，与合同支付方式有关的条款有（ ）。（2016）",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工程量清单错误的修正",false,{"key":16,"text":17,"correct":14},"B","市场价格波动引起的调整",{"key":19,"text":20,"correct":21},"C","预付款比例",true,{"key":23,"text":24,"correct":21},"D","工程进度款支付审批程序",{"key":26,"text":27,"correct":21},"E","质量保证金的扣留与退还","CDE","建设工程施工合同的付款分四个阶段进行，即预付款、工程进度款、最终付款和退还保留金。关于支付时间、支付方式、支付条件和支付审批程序等有很多种可能的选择，并且可能对承包人的成本、进度等产生比较大的影响。 ～275。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]