[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143785":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1143785,799,1,"单选题","关于FIDIC《永久设备和设计—建造合同条件》的说法，正确的是（）。（2018年真题）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","适用于由发包人负责设计的工程项目",false,{"key":16,"text":17,"correct":18},"B","业主委派工程师负责合同管理",true,{"key":20,"text":21,"correct":14},"C","合同计价采用单价合同方式",{"key":23,"text":24,"correct":14},"D","承包商只负责提供设备及工程建造","本题考查的是FIDIC系列合同条件。选项A，适用于由承包商做绝大部分设计的工程项目；选项C，合同计价采用总价合同方式，如果发生法规规定的变化或物价波动，合同价格可随之调整；选项D，承包商要按照业主的要求进行设计、提供设备以及建造其他工程（可能包括由土木、机械、电力等工程的组合）。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]