[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143776":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1143776,799,1,"单选题","在国际工程承包合同中，根据工程项目的规模和复杂程度. DAB争端裁决委员会的任命有多种方式，只在发生争端时任命的是( )。（2013）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","常任争端裁决委员会",false,{"key":16,"text":17,"correct":18},"B","特聘争端裁决委员会",true,{"key":20,"text":21,"correct":14},"C","工程师兼任的委员会",{"key":23,"text":24,"correct":14},"D","业主指定争端裁决委员会","特聘争端裁决委员会，由只在发生争端时任命的一名或三名成员组成，他们的任期通常在DAB对该争端发出其最终决定时期满。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]