[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143757":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143757,799,2,"多选题","（2020年真题）下列影响工程进度因素中,属于承包人可以要求合理延长工期的有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","业主在工程实施中增減工程量对工期产生不利影响",true,{"key":16,"text":17,"correct":14},"B","业主在工程实施中改变工程设计对工期产生不利影响",{"key":19,"text":20,"correct":21},"C","因进场材料不合格而对工期产生不利影响",false,{"key":23,"text":24,"correct":21},"D","因施工操作工艺不规范而对工期产生不利影响",{"key":26,"text":27,"correct":14},"E","突发的极端恶劣的气候对工期产生不利影响","ABE","P332-336 AB为业主原因，E为不可抗力影响。CD是承包商原因。故答案选ABE。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]