[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143754":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143754,799,2,"多选题","（2020年真题）建设工程索赔成立的前提条件有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","与合同对照，事件已造成了承包人工程项目成本的额外支出或直接工期损失",true,{"key":16,"text":17,"correct":14},"B","造成费用增加或工期损失的原因,按合同约定不属于承包人的行为责任或风险责任",{"key":19,"text":20,"correct":21},"C","造成费用增加或工期损失额度巨大,超出了正常的承受范围",false,{"key":23,"text":24,"correct":21},"D","索赔费用计算正确,并且容易分析",{"key":26,"text":27,"correct":14},"E","承包人按合同规定的程序和时间提交了索赔意向通知和索赔报告","ABE","P322-327 索赔的成立，应该同时具备以下三个前提条件: （1）与合同对照，事件已造成了承包人工程项目成本的额外支出，或直接工期损失。 （2）造成费用增加或工期损失的原因，按合同约定不属于承包人的行为责任或风险责任。 （3）承包人按合同规定的程序和时间提交索赔意向通知和索赔报告。 以上三个条件必须同时具备，缺一不可。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]