[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143753":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1143753,799,1,"单选题","（2020年真题）某基础工程合同价为3000万元，合同总工期为30个月，施工过程中因设计变更，导致增加额外工程600万元，业主同意工期顺延。根据比例分析法，承包商可索赔工期（ ）个月。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","4",{"key":19,"text":20,"correct":14},"C","8",{"key":22,"text":23,"correct":24},"D","6",true,"P332-336 如果某干扰事件仅仅影响某单项工程、单位工程或分部分项工程的工期，要分析其对总工期的影响，可以采用比例分析法。 工期索赔值也可以按照造价的比例进行分析。工期索赔值=原合同工期×附加或新增工程造价\u002F原合同总价=30*600\u002F3000=6月",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]