[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143749":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143749,799,2,"多选题","承包人向发包人索赔成立的前提条件有（）。（2018年真题）",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","按合同规定程序和时间提交了索赔报告",true,{"key":16,"text":17,"correct":14},"B","按合同规定程序和时间提交了索赔意向通知",{"key":19,"text":20,"correct":14},"C","与合同对照，事件已造成了承包人实际损失",{"key":22,"text":23,"correct":14},"D","索赔原因按合同约定不属于承包人的行为责任",{"key":25,"text":26,"correct":27},"E","索赔前需进行现场保护",false,"ABCD","本题考查的是索赔成立的条件。索赔的成立，应该同时具备以下三个前提条件：（1）与合同对照，事件已造成了承包人工程项目成本的额外支出，或直接工期损失。（2）造成费用增加或工期损失的原因，按合同约定不属于承包人的行为责任或风险责任。（3）承包人按合同规定的程序和时间提交索赔意向通知和索赔报告。以上三个条件必须同时具备，缺一不可。@##",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]