[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143743":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1143743,799,1,"单选题","（2019年真题）某工程签约合同价为2400万元，总工期为24个月，施工过程中业主增加工程200万元，则根据比例分析法承包商可提出的合理工期索赔值为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1个月",false,{"key":16,"text":17,"correct":18},"B","2个月",true,{"key":20,"text":21,"correct":14},"C","3个月",{"key":23,"text":24,"correct":14},"D","4个月","P328-332 工期索赔值=原合同工期x附加或新增工程造价\u002F原合同总价= 24x 200\u002F2400=2个月",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]