[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143734":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1143734,799,1,"单选题","某工程因发包人原因造成承包人自有施工机械窝工10天，该机械市场租赁费为1200\u002F天，进出厂费2000元，台班费400元\u002F台班，其中台班折旧费160\u002F台班；计划每天工作1台班，共使用40天，则承包人索赔成立的费用是（ ）元。（2016）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","4000",false,{"key":16,"text":17,"correct":18},"B","1600",true,{"key":20,"text":21,"correct":14},"C","12000",{"key":23,"text":24,"correct":14},"D","12500","由于业主或监理工程师原因导致机械停工的窝工费。窝工费的计算，如系租赁设备，一般按实际租金和调进调出费的分摊计算;如系承包人自有设备，一般按台班折旧费计算，而不能按台班费计算，因台班费中包括了设备使用费。 所以索赔成立的费用是160×10＝1600元。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]