[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143730":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143730,799,2,"多选题","建设工程索赔成立的前提条件有( )。（2013）",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","与合同对照，事件已造成了承包人工程项目成本的额外支出或直接工期",true,{"key":16,"text":17,"correct":14},"B","造成费用增加或工期损失的原田，按合同约定不属于承包人的行为责任险责任",{"key":19,"text":20,"correct":14},"C","承包人按合同规定的程序和时间提交索赔意向通知和索赔报告",{"key":22,"text":23,"correct":24},"D","造成费用增加或工期损失额度巨大，超出了正常的承受范围",false,{"key":26,"text":27,"correct":24},"E","索赔费用计算正确，并且容易分析","ABC","索赔的成立，应该同时具备以下三个前提条件： (1)与合同对照，事件已造成了承包人工程项目成本的额外支出，或直接工期损失， (2)造成费用增加或工期损失的原因，按合同约定不属于承包人的行为责任或风险责任， (3)承包人按合同规定的程序和时间提交索赔意向通知和索赔报告。 以上三个条件必须同时具备，缺一不可。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]