[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143724":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1143724,799,1,"单选题","工期延误划分为单一延误、共同延误及交叉延误的依据是（）（2014）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","延误时间之间的关联性",true,{"key":16,"text":17,"correct":18},"B","延误的原因",false,{"key":20,"text":21,"correct":18},"C","索赔要求和结果",{"key":23,"text":24,"correct":18},"D","延误工作所在工程网络计划的线路性质","按照延误事件之间的关联性划分 (1)单一延误(2) 共同延误(3)交叉延误 @##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]