[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143719":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1143719,799,1,"单选题","施工过程中，工程师下令暂停部分工程，而暂停的起因并非承包商违约或其他意外风险，承包商向业主提出索赔，则（ ）。2017",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工期和费用索赔均能成立",true,{"key":16,"text":17,"correct":18},"B","工期和费用索赔均不能成立",false,{"key":20,"text":21,"correct":18},"C","工期索赔成立，费用索赔不能成立",{"key":23,"text":24,"correct":18},"D","工期索赔不能成立，费用索赔能成立","本题考查的是索赔的依据。施工过程中，工程师有权下令暂停全部或任何部分工程，只要这种暂停命令并非承包人违约或其他意外风险造成的，承包人不仅可以得到要求工期延长的权利，而且可以就其停工损失获得合理的额外费用补偿。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]