[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143717":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1143717,799,1,"单选题","某工程项目总价值为1000万元，合同工期为18个月，现因建设条件发生变化而加额外工程费用500万元，则承包方可提出的工期索赔为（ ）。2017",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","27",false,{"key":16,"text":17,"correct":14},"B","24",{"key":19,"text":20,"correct":21},"C","9",true,{"key":23,"text":24,"correct":14},"D","6","本题考查的是工期索赔的计算。如果某干扰事件仅仅影响某单项工程、单位工程或分部分项工程的工期，要分析其对总工期的影响，可以采用比例分析法。工期索赔值可以按照造价的比例进行分析。工期索赔值=原合同工期×附加或新增工程造价\u002F原合同总价=18×500\u002F1000=9个月。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]