[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143715":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1143715,799,1,"单选题","下列干扰事件中，承包商不能提出工其索赔的是( )。（2012）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程师指示承包商加快施工进度",true,{"key":16,"text":17,"correct":18},"B","开工商业主未能及时交付施工图纸",false,{"key":20,"text":21,"correct":18},"C","异常恶劣的气候条件",{"key":23,"text":24,"correct":18},"D","业主未能及时支付工程款造成工期延误","工期索赔的前提是出现了工期延误，而工程师指示加快施工进度不会产生工期延误，因此无法索赔。 @##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]