[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143702":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143702,799,2,"多选题","（2019年真题）合同实施偏差处理的调整措施包括（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","法律措施",false,{"key":16,"text":17,"correct":18},"B","组织措施",true,{"key":20,"text":21,"correct":18},"C","技术措施",{"key":23,"text":24,"correct":18},"D","经济措施",{"key":26,"text":27,"correct":14},"E","监管措施","BCD","P310-314 根据合同实施偏差分析的结果,承包商应该采取相应的调整措施,调整措施可以分为: (1)组织措施,如增加人员投入,调整人员安排,调整工作流程和工作计划等; (2)技术措施,如变更技术方案,采用新的高效率的施工方案等; (3)经济措施,如增加投入,采取经济激励措施等; (4)合同措施,如进行合同变更,签订附加协议,采取索赔手段等。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]