[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143700":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1143700,799,1,"单选题","（2019年真题）下列合同实施偏差处理措施中,属于合同措施的是( )。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","变更施工方案",false,{"key":16,"text":17,"correct":14},"B","调整工作计划",{"key":19,"text":20,"correct":21},"C","采取索赔手段",true,{"key":23,"text":24,"correct":14},"D","增加经济投入","P310-314 合同措施,如进行合同变更,签订协加协议,采取索赔手段等。A属于技术措施; B属于组织措施; C属于经济措施。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]