[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143694":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1143694,799,2,"多选题","下列工程变更情况中，应由业主承担责任的有（）（2014）",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","不可抗力导致的设计修改",true,{"key":16,"text":17,"correct":14},"B","环境变化导致的设计修改",{"key":19,"text":20,"correct":14},"C","原设计错误导致的设计修改",{"key":22,"text":23,"correct":14},"D","政府部门要求导致的设计修改",{"key":25,"text":26,"correct":27},"E","施工方案出现错误导致的设计修改",false,"ABCD","由于业主要求、政府部门要求、环境变化、不可抗力、原设计错误等导致的设计修改，应该由业主承担责任。由此所造成的施工方案的变更以及工期的延长和费用的增加应该向业主索赔。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]