[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143692":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1143692,799,1,"单选题","下列合同实施偏差的调整措施中，属于组织措施的是()（2013）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","增加人员投入",true,{"key":16,"text":17,"correct":18},"B","增加资金投入",false,{"key":20,"text":21,"correct":18},"C","变更技术方案",{"key":23,"text":24,"correct":18},"D","变更合同条款","根据合同实施偏差分析的结果，承包商应该采取相应的调整措施，调整措施可以 分为： ( 1 ) 组织措施，如增加人员投入，调整人员安排，调整工作流程和工作计划等； ( 2 ) 技术措施，如变更技术方案，采用新的高效率的施工方案等； ( 3 ) 经济措施，如增加投入，采取经济激励措施等； ( 4 ) 合同措施，如进行合同变更，签订附加协议，采取索赔手段等。 选项B属于经济措施；选项C属于技术措施；选项D属于合同措施。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]