[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1143680":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1143680,799,1,"单选题","在施工合同实施中，“项目经理将各种任务的责任分解，并落实到具体人员”的活动属于（）的内容（2014）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","合同分析",false,{"key":16,"text":17,"correct":14},"B","合同跟踪",{"key":19,"text":20,"correct":21},"C","合同交底",true,{"key":23,"text":24,"correct":14},"D","合同实施控制","合同交底的目的和任务如下： ( 1 ) 对合同的主要内容达成一致理解； ( 2 ) 将各种合同事件的责任分解落实到各工程小组或分包人； ( 3 ) 将工程项目和任务分解，明确其质量和技术要求以及实施的注意要点等； ( 4 ) 明确各项工作或各个工程的工期要求； ( 5 ) 明确成本目标和消耗标准； ( 6 ) 明确相关事件之间的逻辑关系； ( 7 ) 明确各个工程小组（ 分包人）之间的责任界限； ( 8 ) 明确完不成任务的影响和法律后果；",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]